Flory explains, "To enable the removal of the stacker cranes, about a quarter of the high-bay warehouse was emptied by placing a partial assortment externally and picking it there. Thus, we were able to remove three old stacker cranes at once and install three new ones in just 10 days." Goods in the high-bay warehouse were transferred after their installation and software connection, freeing up the next shelf zone.
Swisslog saved time for the operational ramp-up by doing extensive advance tests on Saturdays and Sundays. Flory concludes: "We are pleased that we were able to play our part in securing the food supply chain at Denner."